Follow Our Progress
Date / Period
23 Nov 2025
Dec 2025
Jan 2026
Feb 2026
Mar 2026
April 2026
May 2026
Activity
Community discussion; Thurleypavilion.com email opens.
Application to register Charitable Incorporated Organisation (CIO)
Project website launches
thursleypavilion.co.uk
Follow up planning pre-app
Apply for CIL funding
Positive Pre-App response from WBC
Clean-up & Update Day 14th March
WBC agreed £100,000 CIL funding grant.
Finalise Planning permission.
Draft Section 38 submission
Commence further ecology surveys following Preliminary Ecology Assessment.
Jun–Aug 2026
End Aug–Early Sep 2026
Preliminaries prior to material start of construction
Demolition/construction commences; 26–30 week build programme
Summer 2027
Completion of New Thursley Pavilion for use during 2027 cricket season.
Official Opening