Follow Our Progress

Date / Period

23 Nov 2025​​​

Dec 2025

Jan 2026

Feb 2026

Mar 2026

April 2026

May 2026

Activity

Community discussion; Thurleypavilion.com email opens.

Application to register Charitable Incorporated Organisation (CIO)

Project website launches  

thursleypavilion.co.uk

Follow up planning pre-app

Apply for CIL funding

Positive Pre-App response from WBC

Clean-up & Update Day 14th March

WBC agreed £100,000 CIL funding grant.

Finalise Planning permission.
Draft Section 38 submission

Commence further ecology surveys following Preliminary Ecology Assessment.

Jun–Aug 2026

End Aug–Early Sep 2026

Preliminaries prior to material start of construction

Demolition/construction commences; 26–30 week build programme

Summer 2027

Completion of New Thursley Pavilion for use during 2027 cricket season.

Official Opening

The pavilion rebuilt in 1965

The pavilion today in a poor state of repair

November 2025 Village Meeting, standing room only, as residents gathered to shape the future of the pavilion