Date / Period

23 Nov 2025​​​

Dec 2025

Activity

Community discussion; email opened for comments; reported in December Parish Magazine. 

Planning Pre-App submitted to WBC; Application filed to register CIO; Engage with pledges of help from within the community; Project website holding pages go live. 

Early Jan

Follow up Pre-App; January Parish Magazine engagement report; Develop full project website. 

Feb 2026

Community Update (1) following Pre-App. 

Launch fundraising via justgiving link on website and in all communications subject to registration as charity.

Mar 2026

May 2026

Jun-Aug 2026

Submit full planning application. 

Grant of planning permission; Community Update (2); Book production time for long-lead construction items.

Preliminaries prior to construction; Community Update (3). 

End Aug-Early Sep 2026

Demolition/constructions starts; 26-30 week build; Community Update (4).

Early 2027

Completion of new pavilion; Community Update (5). 